The auger and tower stands Feb. 21 on two of the coming Dusty grain pads project.
Construction began last September, for the McCoy Land Company/PNW project which will include grain piles, truck scales, utilities and a small office space, with a driveway off Highway 127 south of Dusty.
The height of the piles will go to 65 feet. Phase one of the four-pile project is scheduled to be finished in June.
Stage two would start after harvest 2020, to be done by June of the next year.